Wednesday 17 December 2014

Group Meetings - Miss Georgiou

The meetings, disscussions and plannings are vital to the production of our thriller films. It allowed us to build a bases for the various micro elements and used within our thriller films, the plot of our sequence and to plan out the production so that it is filmed as efficiently as possible. The discussions allowed us to get a more rounded view on different ideas and opinions applied to the film so that we could produce the most conventional sequence possible.

As a whole I felt that the communication between the group within the planning and discussions throughout the process was very good. We each agreed on the ideas and micro elements in a civil, professional manner allowing the planning and preparation process to run very smoothly. However, although both being very co-operative I would also like to have seen a more rounded effort during the meetings. I felt that in many cases throughout the process I was left with most of the responsibility for the tasks having to bring forth and provide a lot of the ideas and micro elements throughout the discussions. I would have like to have seen more contribution from the other group members.


Date
Action
To be done by
By whom
Discussions  
15.09.14
To decide a group narrative
15.09.14
All group members
Various ideas were discussed and a mindmap was created by the group. Eventually we decided on a narrative about….

Planning the opening sequence



19.09.14
Planning the opening sequence
19.09.14
All group members
Within this meeting we had a discussion into the general presentation of the sequence, the layout and the different microelements.
24.09.14
Planning mise en scene
24.09.14
All group members
We discussed the mes en scene shown throughout the film including; the presentation of characters, iconography and setting
30.09.14
Elements, examples and effects created
30.09.14
All group members

3.10.14
Planning sounds
3.10.14
All group members
We decided upon the different sounds used to effect in the clip. Specifically thinking of a sound for each scene 
8. 09.14
Planning editing styles
8. 09.14
All group members
We discussed specific ways in which we can use our editing techniques to good effect
15.09.14
Planning opening credits
15.09.14
All group members
We each designed our individual credits, putting them together and deciding about the final credits seen in our sequence
20.09.14
Planning characters
20.09.14
All group members
We talked, in detail, about the names of each character in the sequence and how they will be presented in the sequence
27.0914
Group story board
27.0914
All group members
During this meeting we put together our different individual story boards and came to a final idea about how we are going to produce our clip
31.09.14
Filming schedule and risk assessment
31.09.14
All group members
We developed pur filming schedule and risk assessment to insure that our filming and editing went smoothly and efficiently
5.12.14
Filming the thriller
5.12.14
All group members
The filming itself was split into various days. We used our storyboard and film schedule to insure it went to plan

1 comment:

  1. You have made a start in describing what the purpose of group meetings are and the benefit it had to your production. However, you need to explore why you think you and your group did not work well together in further detail, by focusing on the issues and how you overcame them.

    The table that you have included helps to demonstrate the meetings that you had, but you need to ensure that you have completed it, by adding editing, soundtrack and credits to it.

    You also need to include the group planning sheets to complete this post and to demonstrate further evidence of how you and your group worked well together.

    ReplyDelete